Does halfway in time mean that the progress of work that needs to be done is 50%? Let’s check that with some facts.
Old House
Still needs to be done
Ready
Removing laminate flooring from:
Removed laminate flooring from:
-          Room in the attic
-          Study
-          Living room, kitchen +hallway downstairs
-          Hallway from the attic floor
Packing paraphernalia from:
Packed paraphernalia from:
-          Bathroom
-          Study
-          Hallway attic floor
-          Stairway walls
-          Hallway downstairs
-          Hallway first floor
-          Living room
-          Master bedroom
-          Kitchen
-          Upper attic (storage space)
Backyard:
Backyard:
-          Leveling the crater with the terraces
-          Removed and transported the trampoline
-          Dig up the roses
-          Moved the Aster, the Hydrangeas and various plants in pots
Various things that need to be repaired or replaced:

-          Big screw from banisters

-          Washing stand bathroom

New House
Wallpaper removal:
Wallpaper removed:
-          Two smallest bedrooms
-          Living room
-          Bigger bedroom (almost done)
-          Kitchen
-          Master bedroom (almost done)

-          Hallway downstairs
Removed:
-          Hallway upstairs
-          Vertical blinds downstairs
Plastering walls from:
-          Curtains and horizontal blinds upstairs
-          4 bedrooms
-          Moved 3 closets from first floor to attic (first disassemble and then after carrying them upstairs assemble them again)
-          Living room/kitchen

-          Stairway plus hallways
Moved:
Laying floors:
-          Laminate in 3 bedrooms plus hallway upstairs
-          Carpet in my bedroom
-          Winter clothes from old to new house
-          Half the stuff from the upper attic from old to new house
-          Pebbles from backyard old house to new house
-          Moved terrace tiles from new house backyard to old house (to replace the pebblestone path in backyard)
Painting walls in the whole house but not necessarily all before moving the furniture

Hanging lamps, pictures and shelves




Almost 50-50. Probably I forgot something here but then I’ll remember it before falling asleep. Last night I dreamt that there has a huge pile of sand been delivered in the street here. My neighbors had ordered that. I remembered feeling confused about it because I already made a lot of effort to fill the crater.